THE BRIDGE I
"DESIGN FOR FUNCTION"
INSTRUCTOR
OVERVIEW OF THIS PROJECT AND WHAT TO EXPECT
This is the first part of two projects; the projects should be
done in order. This project entails designing, building, and
testing a bridge. The bridges will be constructed by groups of
three to four students. The students will learn that sometimes
the specifications given are conflicting. In particular the
strength and weight of a bridge are conflicting specifications.
When this occurs the designer must often use creative solutions
to solve the problem.
SPECIFIC PURPOSE OF THIS PROJECT
The purpose of this project is to give students a exciting way to
learn how different materials have vastly different properties.
Some materials work only in tension while some materials work
best in compression. Also, materials don't have to be heavy to
be strong; styrofoam is light and works well in compression.
String is very light also, but it only works in tension. This
project also, helps students understand that the specifications
of products often conflict.
THE REAL-WORLD PROBLEM RELATED TO THE PROJECT
Engineers must understand the properties of materials and how
they are most efficiently used. This project gives students the
chance to try their hand at solving a real-world problem (making
strong light structures) while investigating the ramifications of
the materials chosen. This is an excellent chance to watch how
structures fail, which is another branch of engineering.
SPACE AND TIME REQUIRED/DESIRABLE
Each team will require a table top area with dimensions
approximately three feet by three feet. It should take a team
approximately three to fours hours to build a bridge. We
recommend doing this project only once with the students before
trying the second part.
MATERIALS AND EQUIPMENT NEEDED
A bridge may consist of the following:
- 5 blocks of styrofoam (.75 x 10 x 5) inches
- 5 rubber bands
- 10 paper clips
- 1 piece of wood (3.75 x 3.75 x 3.75) inches
- 10 nails
- 16 inches of clear tape, max width 1 inch
- all the spaghetti you want
- 2-2 liter soda bottles (empty or full of original contents or
water)
- 1 foot wooden dowel rod, diameter _ 1/2 inch
- 4 feet of string
- 1 hook that has wood threads on one end
The styrofoam may be cut from a standard 8 foot by 4 foot sheet
that is .75 inches thick. We have found that a table saw does a
good job of cutting the styrofoam. The wood block can be cut
from a 4-by-4. It is best to give each group the materials
allowed them, this keeps them from using more then they are
allotted. You should allow them the use of any tools at your
disposal that seem reasonable (typically - hammer, pliers, drill,
cutting tool, etc.)
SUGGESTIONS REGARDING STUDENT TEAMS
The students should be divided into teams of no more than five
and no less than three.
PREPARING FOR THIS PROJECT - WHAT TO DO IN ADVANCE
You must construct the stand that the students will test their
bridges on. The easiest way is to use two heavy tables that
stand the same height. Tape off a 6"x6" square on the top next
to the edge of each table and set them two feet apart. Now you
must put boxes, chairs, books, or what ever is convenient to
build up the "valley" to be only two foot from the top of the
table.

Figure 1.
A better method is to build a stand from 4-by-4's, plywood, nails
and four threaded rods, and eight nuts. The finished product is
shown in figure 1.
You also need to gather the materials for the students bridges,
as well as the tools that you will allow them to use. A basket
to hang from the bridge must also be acquired as well as weights
to put in the basket. Ten kilograms of weight broken up into
half kilograms should be adequate to break any bridge.
SUGGESTIONS FOR MANAGING THE PROJECT
- Divide the class into design teams.
- Distribute the Student Project Description.
- Present the project to the students (15-20 minutes).
- Let the students read the materials, discuss it among
themselves, ask questions, and generate design ideas (30
minutes).
- Have students present their ideas or comment on their
proposed designs. You should interact to help steer them clear
of obviously bad designs eg. filling both 2 liter bottles with
water.
- Allow students to work on projects (2-4 hours).
- Test the final designs (.5-1 hour).
- Summarize the results of the project and tie the concepts
together in a positive closure (20-40 minutes).
GUIDELINES FOR TESTING THE PRODUCTS
The bridges must touch only the tops of 2 platforms that are
6"x6" and spaced 2' apart (see figure 1). All bridges must rest
on the platforms during the entire testing process. A team may
not nail, screw, drill, or otherwise modify or attach to the
platforms.
Before you may destroy the students bridges you must weigh them
and record this weight. In order for you to test the bridges,
the students must attach the eye hook provided to the bottom,
center of their bridge. Only the hook can extend below the 2
foot level (top of the abutments). You should slowly and
carefully load the weights into the basket until the basket hits
the two foot mark. Then record this weight. The score is
computed as follows:
SPI = weight supported (grams) / weight of your bridge (grams)
PROVIDING SUCCESSFUL CLOSURE
In particular we encourage you in this project to emphasize the
problems associated with conflicting specifications. Nearly all
products have this problem, therefore creative solutions are
always being sought to deal with the design specifications.
This project illustrates that engineering design requires the
incorporation of knowledge from multi-disciplinary fields,
conflicting objectives, and multiple goals. This is what makes
engineering challenging; however, when students loose sight of
these overall goals and begin to become obsessed with design
details, their designs will become less successful. Even the
brightest and most creative students can fall into this trap.
Most designs, even less successful ones, have strong points.
Acknowledging those points along with some constructive criticism
helps the students learn some of the more difficult points. We
have found that group discussion following testing in which each
team or individual critiques the strong and weak features of
their own design is fruitful.
Finally, please make a special point of reminding students that
this kind of creative activity is at the heart of engineering.
If they found the project enjoyable, they should consider
engineering as a profession.
SPECIAL SAFETY CONSIDERATIONS
It is important that no part of your body or your students bodies
be under the weights while a bridge is being tested. Also
remember to be sure the students know how to use the tools and
that they exercise caution when using them.
This project was developed by Michael I. Hessel, Jr.